20.2 Quality and Process
A software plan involves many intertwined concerns, from schedule to cost to usability and dependability. Despite the intertwining, it is useful to distinguish individual concerns and objectives to lessen the likelihood that they will be neglected, to allocate responsibilities, and to make the overall planning process more manageable.
For example, a mature software project plan will include architectural design reviews, and the quality plan will allocate effort for reviewing testability aspects of the structure and build order. Clearly, design for testability is an aspect of software design and cannot be carried out by a separate testing team in isolation. It involves both test designers and other software designers in explicitly evaluating testability as one consideration in selecting among design alternatives. The objective of incorporating design for testability in the quality process is primarily to ensure that it is not overlooked and secondarily to plan activities that address it as effectively as possible.
An appropriate quality process follows a form similar to the overall software process in which it is embedded. In a strict (and unrealistic) waterfall software process, one would follow the "V model" (Figure 2.1 on page 16) in a sequential manner, beginning unit testing only as implementation commenced following completion of the detailed design phase, and finishing unit testing before integration testing commenced. In the XP "test first" method, unit testing is conflated with subsystem and system testing. A cycle of test design and test execution is wrapped around each small-grain incremental development step. The role that inspection and peer reviews would play in other processes is filled in XP largely by pair programming. A typical spiral process model lies somewhere between, with distinct planning, design, and implementation steps in several increments coupled with a similar unfolding of analysis and test activities. Some processes specifically designed around quality activities are briefly outlined in the sidebars on pages 378, 380, and 381.
A general principle, across all software processes, is that the cost of detecting and repairing a fault increases as a function of time between committing an error and detecting the resultant faults. Thus, whatever the intermediate work products in a software plan, an efficient quality plan will include a matched set of intermediate validation and verification activities that detect most faults within a short period of their introduction. Any step in a software process that is not paired with a validation or verification step is an opportunity for defects to fester, and any milestone in a project plan that does not include a quality check is an opportunity for a misleading assessment of progress.
The particular verification or validation step at each stage depends on the nature of the intermediate work product and on the anticipated defects. For example, anticipated defects in a requirements statement might include incompleteness, ambiguity, inconsistency, and overambition relative to project goals and resources. A review step might address some of these, and automated analyses might help with completeness and consistency checking.
The evolving collection of work products can be viewed as a set of descriptions of different parts and aspects of the software system, at different levels of detail. Portions of the implementation have the useful property of being executable in a conventional sense, and are the traditional subject of testing, but every level of specification and design can be both the subject of verification activities and a source of information for verifying other artifacts. A typical intermediate artifact - say, a subsystem interface definition or a database schema - will be subject to the following steps:
Internal consistency check Check the artifact for compliance with structuring rules that define "well-formed" artifacts of that type. An important point of leverage is defining the syntactic and semantic rules thoroughly and precisely enough that many common errors result in detectable violations. This is analogous to syntax and strong-typing rules in programming languages, which are not enough to guarantee program correctness but effectively guard against many simple errors.
External consistency check Check the artifact for consistency with related artifacts. Often this means checking for conformance to a "prior" or "higher-level" specification, but consistency checking does not depend on sequential, top-down development - all that is required is that the related information from two or more artifacts be defined precisely enough to support detection of discrepancies. Consistency usually proceeds from broad, syntactic checks to more detailed and expensive semantic checks, and a variety of automated and manual verification techniques may be applied.
Generation of correctness conjectures Correctness conjectures, which can be test outcomes or other objective criteria, lay the groundwork for external consistency checks of other work products, particularly those that are yet to be developed or revised. Generating correctness conjectures for other work products will frequently motivate refinement of the current product. For example, an interface definition may be elaborated and made more precise so that implementations can be effectively tested.